| Dự án | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC |
|---|---|---|---|---|---|---|---|---|---|---|
| GoMS |
W2
DMS Requirement Brief
W3
Vendor Sourcing
W4
Vendor Sourcing
|
W1
Briefing Round
W2
Briefing Round
W3
Pitching & Refine Requirements
W4
Pitching & Refine Requirements
|
W1
Present Proposal Round
W2
Present Proposal Round
W3
Finalize Pricing & Contract
W4
Finalize Vendor
|
W1
Pitching & Contract: Pitching DMS R1 - FinViet, DMS Pro, HQ Soft
W2
Pitching & Contract: Pitching DMS R final - FinViet
W3
Pitching & Contract: Contract Scope & Term review
W4
Pitching & Contract: Kick off
|
W1
Discovery: Business Requirement Workshop
W2
Discovery: Infrastructure & ERP - GoMS Integration Workshop
W3
Design: Solution Design
W4
Design: 2-Phase Blueprint Sign-off
|
W1
Development Phase 1: UAT Environment Setup
W2
Testing Phase 1: System Integration Testing ERP & GoMS
W3
Testing Phase 1: System Integration Testing EOffice & GoMS
W4
Deployment & Pilot Phase 1: UAT Data Ready - Masterdata
|
W1
Deployment & Pilot Phase 1: UAT Data Ready - Data kho, vùng miền, KH, sales, pricing, BU, CTKM, hoa hồng
W2
Deployment & Pilot Phase 1: UAT Test Case Preparation
W3
Deployment & Pilot Phase 1: Training key user dùng DMS
W4
Deployment & Pilot Phase 1: Key user dùng thử DMS
|
W1
Deployment & Pilot Phase 1: UAT Sign-off
W2
Deployment & Pilot Phase 1: Production Environment Setup - Masterdata final, Infrastructure
W3
Deployment & Pilot Phase 1: Data Migration - cập nhật Data kho, vùng miền, KH, sales, pricing, BU, CTKM, hoa hồng
W4
Deployment & Pilot Phase 1: Training all users dùng DMS
|
Go-live: GoMS Phase 1 (SFA + TPM)
W1
Go-live Phase 1: Phase 1 Go-live
Discovery Phase 2: Business Requirement Workshop = Forecast, B2B Portal
W2
Hypercare Phase 1: Pilot Deployment Accepted (WEB)
Discovery Phase 2: All system Integration Workshop
W3
Hypercare Phase 1: Pilot Deployment Accepted (APP)
Design Phase 2: Blueprint Sign-off
W4
Hypercare Phase 1: Hypercare Completed
Development Phase 2: UAT Environment Setup (Forecast on TPM & SFA)
|
Go-live: GoMS Phase 2 (Forecast + B2B Portal)
W1
Development Phase 2: B2B development
W2
Testing Phase 2: SIT & UAT
W3
Deployment & Pilot Phase 2: Data Import (Forecast)
W4
Go-live Phase 2: Phase 2 Go-live
|
| User liên quan |
|
|||||||||
| Vendors |
W3
FinViet draft contract
W4
FinViet gửi kế hoạch dự án
|
W1
FinViet lấy yêu cầu nghiệp vụ (Business Requirement Workshop)
W2
FinViet lấy yêu cầu nghiệp vụ (Infrastructure & ERP-GOMS Integration Workshop)
W3
FinViet đề xuất phương án (Solution Design)
W4
FinViet config (2-Phase Blueprint Sign-off)
|
W1
FinViet config (UAT Environment Setup)
W2
FinViet config (SIT ERP & GoMS)
W3
FinViet - BTM hoàn tất SIT (EOffice & GoMS)
W4
FinViet chuẩn bị đầy đủ môi trường & dữ liệu UAT, User Guide cho Key User
|
W1
FinViet chuẩn bị đầy đủ môi trường & dữ liệu UAT (Data kho, vùng miền, KH, sales, pricing, BU, CTKM, hoa hồng)
W2
FinViet phối hợp cùng Vigo thống nhất kịch bản UAT
W3
FinViet train (key user dùng DMS)
W4
FinViet support (Key user dùng thử DMS)
|
W1
FinViet support (UAT Sign-off)
W2
FinViet hoàn thành chuẩn bị môi trường, tích hợp & dữ liệu cho Go-live
W3
FinViet config & integrate ERP, EOffice (Data Migration)
W4
FinViet train (Training all users dùng DMS)
|
W1
FinViet support (Go-live Phase 1)
FinViet lấy yêu cầu nghiệp vụ (Discovery Phase 2)
W2
FinViet triển khai Pilot & xác nhận vận hành Web (Hypercare Phase 1)
FinViet lấy yêu cầu nghiệp vụ (All system Integration Workshop - Phase 2)
W3
FinViet triển khai Pilot & xác nhận vận hành App (Hypercare Phase 1)
FinViet đề xuất phương án (Blueprint Sign-off - Phase 2)
W4
Hoàn tất hỗ trợ sau Pilot (Hypercare Phase 1)
FinViet config (UAT Environment Setup - Phase 2)
|
W1
FinViet dev (Phase 2_B2B development)
W2
FinViet config (SIT & UAT)
W3
FinViet train & config (Data Import_Forecast)
W4
FinViet support (Go-live Phase 2)
|
|||
| STRAT |
W3
STRAT coordinate
W4
STRAT coordinate
|
W1
STRAT coordinate
W2
STRAT join & share
W3
STRAT coordinate
W4
STRAT prepare infrastructure
|
W1
STRAT prepare infrastructure
W2
STRAT prepare infrastructure
W3
STRAT hoàn tất SIT
W4
STRAT chuẩn bị đầy đủ môi trường & dữ liệu UAT, User Guide cho Key User
|
W1
STRAT chuẩn bị đầy đủ môi trường & dữ liệu UAT cho Key User
W2
STRAT phối hợp cùng Vigo thống nhất kịch bản UAT
W3
STRAT coordinate
W4
STRAT coordinate
|
W1
STRAT hoàn thành kiểm thử và xác nhận hệ thống
W2
STRAT tích hợp CORE MAPPING & training
W3
STRAT config
W4
STRAT xác nhận tất cả điều kiện Go-live đã sẵn sàng
|
W1
STRAT support (Go-live Phase 1)
STRAT coordinate (Discovery Phase 2)
W2
STRAT support (Hypercare Phase 1)
STRAT join & share (Integration Workshop - Phase 2)
W3
STRAT support (Hypercare Phase 1)
STRAT coordinate (Blueprint Sign-off - Phase 2)
W4
STRAT support (Hypercare Phase 1)
STRAT prepare infrastructure (UAT Environment Setup - Phase 2)
|
W1
STRAT coordinate
W2
STRAT test integration và phản hồi
W3
STRAT xác nhận tất cả điều kiện Go-live đã sẵn sàng
W4
STRAT support
|
|||
| BOD |
W1
CEO join & share (Business Requirement Workshop)
W4
CEO join & align (Blueprint Sign-off)
|
W4
CEO join & align (UAT Data Ready - Masterdata)
|
W2
CEO join & align (UAT Test Case Preparation)
|
W1
CEO join & align (UAT Sign-off)
|
W1
CEO join & share (Discovery Phase 2)
W3
CEO join & align (Blueprint Sign-off - Phase 2)
|
|||||
| FIN |
W1
FIN join & share (Business Requirement Workshop)
|
W1
FIN fill in data (UAT Data Ready)
|
W3
FIN review data (Data Migration)
|
W1
FIN phản hồi
W2
FIN phản hồi
W3
FIN phản hồi
W4
FIN xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
FIN phản hồi (Development Phase 2)
|
W1
FIN phản hồi
W2
FIN phản hồi
W3
FIN phản hồi
W4
FIN xác nhận độ hoàn thiện của GOMS
|
|||||
| ACC |
W1
ACC join & share (Business Requirement Workshop)
|
W4
ACC fill in data (UAT Data Ready)
|
W1
ACC fill in data (UAT Data Ready)
|
W3
ACC review data (Data Migration)
|
W1
ACC phản hồi - dừng MISA CRM
W2
ACC phản hồi
W3
ACC phản hồi
W4
ACC xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
ACC phản hồi (Development Phase 2)
|
W1
ACC phản hồi
W2
ACC phản hồi
W3
ACC phản hồi
W4
ACC xác nhận độ hoàn thiện của GOMS
|
||||
| HR |
W1
HR join & share (Business Requirement Workshop)
|
W1
HR fill in data (UAT Data Ready)
|
W3
HR review data (Data Migration)
|
W1
HR phản hồi
W2
HR phản hồi
W3
HR phản hồi
W4
HR xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
HR phản hồi (Development Phase 2)
|
W1
HR phản hồi
W2
HR phản hồi
W3
HR phản hồi
W4
HR xác nhận độ hoàn thiện của GOMS
|
|||||
| SALES |
W1
SALES join & share (Business Requirement Workshop)
W3
SALES align solution (Solution Design)
|
W4
SALES fill in data (UAT Data Ready)
|
W1
SALES fill in data trên CORE MAPPING (UAT Data Ready)
W2
SALES fill in data trên CORE MAPPING (UAT Test Case Preparation)
W3
SALES join training (key user dùng DMS)
W4
SALES dùng thử DMS
|
W1
SALES dùng thử DMS (UAT Sign-off)
W2
SALES dùng thử CORE MAPPING (Production Environment Setup)
W3
SALES review data (Data Migration)
W4
SALES join training (Training all users)
|
W1
SALES dùng Hệ thống DMS - dừng MISA CRM (Go-live Phase 1)
SALES phản hồi (Discovery Phase 2)
W2
SALES phản hồi
W3
SALES phản hồi
W4
SALES xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
SALES phản hồi (Development Phase 2)
|
W1
SALES phản hồi
W2
SALES phản hồi
W3
SALES phản hồi
W4
SALES xác nhận độ hoàn thiện của GOMS
|
||||
B2B Web Portal dự kiến ra mắt tháng 01/2027 sau Go-live tháng 9/2026.