Hoàn thành
Đang thực hiện
Sắp tới
Không có
| Dự án | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC |
|---|---|---|---|---|---|---|---|---|---|---|
| ERP |
W1
Finalize Contract
W2
Project Master Plan Preparation
W3
Project Team Preparation
W4
Project Kick-off
|
W1
Business Requirement Gathering
W2
Business Requirement Gathering
W3
Blueprint Preparation
W4
Blueprint Preparation
|
W1
System Configuration
W2
System Configuration
W3
System Configuration
W4
System Configuration
|
W1
Unit Test
W2
Unit Test
W3
System Integration Testing
W4
System Integration Testing
|
W1
DMS + EOffice Integration + E-Invoice
W2
DMS + EOffice Integration + E-Invoice
W3
DMS + EOffice Integration Testing + E-Invoice
W4
DMS + EOffice Integration Testing + E-Invoice
|
W1
Train the Trainer
W2
Train the Trainer
W3
User Acceptance Test
W4
Master Data Cutover
|
Go-live: ERP
|
W1
Hypercare
W2
Hypercare
W3
Hypercare
W4
Hypercare
|
W1
Hypercare
W2
Hypercare
W3
Hypercare
W4
Hypercare
|
W1
Hypercare
W2
Hypercare
W3
Hypercare
W4
Hypercare
|
| User liên quan |
|
|||||||||
| Vendors |
W4
BTM sign contract
|
W1
BTM gửi kế hoạch dự án
W2
BTM lấy yêu cầu nghiệp vụ (Discovery - Business)
W3
BTM lấy yêu cầu nghiệp vụ (Discovery - ACC)
W4
BTM lấy yêu cầu nghiệp vụ (Discovery - FIN)
|
W1
BTM lấy yêu cầu nghiệp vụ (Discovery - SC)
W2
BTM lấy yêu cầu nghiệp vụ (Bizzi)
W3
BTM FIT/GAP
W4
BTM đề xuất phương án GAP closing
|
W1
BTM đề xuất phương án GAP closing
W2
BTM thiết lập cấu hình NetSuite theo FIT/GAP
W3
BTM thiết lập cấu hình NetSuite theo FIT/GAP
W4
BTM thiết lập cấu hình NetSuite theo FIT/GAP
|
W1
BTM & Bizzi integrate
W2
BTM & FinViet integrate (GoMS/DMS)
W3
BTM & Base integrate (EOffice)
W4
BTM train key user NetSuite (FIN, ACC, SC)
|
W1
BTM config - Migration data đợt 1 (Sandbox)
W2
BTM train - MRP (SC)
W3
BTM config - Migration data đợt 2
W4
BTM config - SIT/UAT
|
W1
BTM config - Migration data đợt 3 (Production)
W2
BTM config - Go-live
W3
BTM hypercare
W4
BTM hypercare
|
W1
BTM hypercare
W2
BTM hypercare
W3
BTM hypercare
W4
BTM hypercare
|
W1
BTM hypercare
|
|
| STRAT |
W4
STRAT coordinate
|
W1
STRAT coordinate
W2
STRAT coordinate
W3
STRAT coordinate
W4
STRAT coordinate
|
W1
STRAT coordinate
W2
STRAT coordinate
W3
STRAT coordinate
W4
STRAT coordinate
|
W1
STRAT coordinate
W2
STRAT prepare infrastructure
W3
STRAT prepare infrastructure
W4
STRAT prepare infrastructure
|
W1
STRAT prepare infrastructure
W2
STRAT prepare infrastructure
W3
STRAT prepare infrastructure
W4
STRAT coordinate
|
W1
STRAT frame Masterdata & import data
W2
STRAT coordinate
W3
STRAT config
W4
STRAT test tích hợp hệ thống ERP & phản hồi
|
W1
STRAT config
W2
STRAT config
W3
STRAT support
W4
STRAT support
|
W1
STRAT support
W2
STRAT support
W3
STRAT support
W4
STRAT support
|
W1
STRAT support
|
|
| BOD |
W2
CEO join & share (workshop Business)
|
W1
CEO review Master data
|
||||||||
| FIN |
W4
FIN join & share (workshop Accounting & Financial)
|
W2
FIN brief Bizzi
W4
FIN align solution
|
W4
FIN join training NetSuite
|
W1
FIN review Master data
W4
FIN sử dụng thử hệ thống ERP và phản hồi (UAT)
|
W2
FIN sử dụng hệ thống ERP (Go-live)
W3
FIN phản hồi
W4
FIN phản hồi
|
W1
FIN phản hồi
W2
FIN phản hồi
W3
FIN phản hồi
W4
FIN phản hồi
|
W1
FIN phản hồi
|
|||
| ACC |
W3
ACC join & share (workshop Order to Cash)
|
W2
ACC brief Bizzi
W4
ACC align solution
|
W4
ACC join training NetSuite
|
W1
ACC review Master data
W3
ACC support verify (chuẩn hóa dữ liệu KH)
W4
ACC sử dụng thử hệ thống ERP và phản hồi (UAT)
|
W2
ACC sử dụng hệ thống ERP, dùng song song MISA (Go-live)
W3
ACC dùng song song NetSuite - MISA và phản hồi
W4
ACC dùng song song NetSuite - MISA và phản hồi
|
W1
ACC dùng song song NetSuite - MISA và phản hồi
W2
ACC dùng song song NetSuite - MISA và phản hồi
W3
ACC dùng song song NetSuite - MISA và phản hồi
W4
ACC dùng song song NetSuite - MISA và phản hồi
|
W1
ACC dùng song song NetSuite - MISA và phản hồi
|
|||
| SC |
W1
SC join & share (workshop Inventory & MRP)
W4
SC align solution
|
W4
SC join training NetSuite
|
W1
SC review Master data
W2
SC join training (MRP)
W4
SC sử dụng thử hệ thống ERP và phản hồi (UAT)
|
W2
SC sử dụng hệ thống ERP (Go-live)
W3
SC phản hồi
W4
SC phản hồi
|
W1
SC phản hồi
W2
SC phản hồi
W3
SC phản hồi
W4
SC phản hồi
|
W1
SC phản hồi
|
||||
| HR |
W1
HR review Master data
|
|||||||||
| SALES |
W3
SALES fill in customer form từ ACC (chuẩn hóa dữ liệu KH)
|
|||||||||
| LEGAL |
W3
LEGAL fill form Product - Hồ sơ pháp lý
|
|||||||||
| MKT |
W3
MKT fill form Product - Giấy phép quảng cáo
|
|||||||||
| MEDICAL |
W1
MED review Master data
|
|||||||||
| HRM - eOffice |
HRM Requirement Brief
Sourcing Vendor
|
Pitching Round 1
Pitching Round 2
Finalize Vendor
|
Finalize Contract
Project Master Plan Preparation
Project Team Preparation
Project Kick-off
|
W1
Pitching & Contract: Pitching EOFFICE-HRM vendors (BASE, 1Office)
W2
Pitching & Contract: Selection vendor - price negotiation (BASE)
W3
Pitching & Contract: Kick-off khởi động dự án
W4
Pitching & Contract: Contract
|
W1
Discovery (EOFFICE): Liệt kê hệ thống quy trình, danh mục số hóa
Discovery (HRM): Business Requirement Workshop cùng HR
W2
Design (EOFFICE): Tái thiết kế hệ thống quy trình
Design (HRM): Chuẩn bị dữ liệu nhân sự
W3
Development (EOFFICE): Hướng dẫn thiết lập hệ thống EOFFICE
Development (HRM): Hướng dẫn thiết lập hệ thống E-Hiring và Hrm+
W4
Testing (EOFFICE): Kiểm thử hệ thống tích hợp với ERP, GOMS
Testing (HRM): Kiểm thử hệ thống nhân sự, bảng công, bảng lương
|
Go-live: EOFFICE (Work+) & HRM (Hrm+)
W1
Deployment & Pilot (EOFFICE): Thực hiện training all Vigo sử dụng EOFFICE (Work+)
Deployment & Pilot (HRM): Thực hiện training all Vigo sử dụng Base HRM (Hrm+)
W2
Go-live (EOFFICE): Go live EOFFICE (Work+)
Go-live (HRM): Go live HRM (Hrm+)
W3
Hypercare: Review hệ thống và tối ưu sau vận hành chính thức
W4
Hypercare (EOFFICE): Review hệ thống và tối ưu sau vận hành chính thức
Hypercare (HRM): Review chạy bảng công, bảng lương Tháng 8, Tháng 9, Tháng 10
|
|
|
|
|
| User liên quan |
|
|||||||||
| STRAT |
W4
STRAT coordinate
|
W1
STRAT join & share
W2
STRAT coordinate
W3
STRAT & BASE train
W4
STRAT config
|
W1
STRAT train
W2
STRAT support
W3
STRAT support
W4
STRAT support
|
|||||||
| BOD |
W2
CEO join & align
W4
CEO join & align
|
|||||||||
| FIN |
W1
FIN join training
|
|||||||||
| ACC |
W1
ACC join training
|
|||||||||
| SC |
W1
SC join training
|
|||||||||
| HR |
W2
HR fill in data
|
W1
HR join training
W4
HR xác nhận độ hoàn thiện của HRM, EOFFICE
|
||||||||
| SALES |
W1
SALES join training
|
|||||||||
| LEGAL |
W1
LEGAL join training
|
|||||||||
| MKT |
W1
MKT join training
|
|||||||||
| MEDICAL |
W1
MEDICAL join training
|
|||||||||
| GoMS |
W2
DMS Requirement Brief
W3
Vendor Sourcing
W4
Vendor Sourcing
|
W1
Briefing Round
W2
Briefing Round
W3
Pitching & Refine Requirements
W4
Pitching & Refine Requirements
|
W1
Present Proposal Round
W2
Present Proposal Round
W3
Finalize Pricing & Contract
W4
Finalize Vendor
|
W1
Pitching & Contract: Pitching DMS R1 - FinViet, DMS Pro, HQ Soft
W2
Pitching & Contract: Pitching DMS R final - FinViet
W3
Pitching & Contract: Contract Scope & Term review
W4
Pitching & Contract: Kick off
|
W1
Discovery: Business Requirement Workshop
W2
Discovery: Infrastructure & ERP - GoMS Integration Workshop
W3
Design: Solution Design
W4
Design: 2-Phase Blueprint Sign-off
|
W1
Development Phase 1: UAT Environment Setup
W2
Testing Phase 1: System Integration Testing ERP & GoMS
W3
Testing Phase 1: System Integration Testing EOffice & GoMS
W4
Deployment & Pilot Phase 1: UAT Data Ready - Masterdata
|
W1
Deployment & Pilot Phase 1: UAT Data Ready - Data kho, vùng miền, KH, sales, pricing, BU, CTKM, hoa hồng
W2
Deployment & Pilot Phase 1: UAT Test Case Preparation
W3
Deployment & Pilot Phase 1: Training key user dùng DMS
W4
Deployment & Pilot Phase 1: Key user dùng thử DMS
|
W1
Deployment & Pilot Phase 1: UAT Sign-off
W2
Deployment & Pilot Phase 1: Production Environment Setup - Masterdata final, Infrastructure
W3
Deployment & Pilot Phase 1: Data Migration - cập nhật Data kho, vùng miền, KH, sales, pricing, BU, CTKM, hoa hồng
W4
Deployment & Pilot Phase 1: Training all users dùng DMS
|
Go-live: GoMS Phase 1 (SFA + TPM)
W1
Go-live Phase 1: Phase 1 Go-live
Discovery Phase 2: Business Requirement Workshop = Forecast, B2B Portal
W2
Hypercare Phase 1: Pilot Deployment Accepted (WEB)
Discovery Phase 2: All system Integration Workshop
W3
Hypercare Phase 1: Pilot Deployment Accepted (APP)
Design Phase 2: Blueprint Sign-off
W4
Hypercare Phase 1: Hypercare Completed
Development Phase 2: UAT Environment Setup (Forecast on TPM & SFA)
|
Go-live: GoMS Phase 2 (Forecast + B2B Portal)
W1
Development Phase 2: B2B development
W2
Testing Phase 2: SIT & UAT
W3
Deployment & Pilot Phase 2: Data Import (Forecast)
W4
Go-live Phase 2: Phase 2 Go-live
|
| User liên quan |
|
|||||||||
| Vendors |
W3
FinViet draft contract
W4
FinViet gửi kế hoạch dự án
|
W1
FinViet lấy yêu cầu nghiệp vụ (Business Requirement Workshop)
W2
FinViet lấy yêu cầu nghiệp vụ (Infrastructure & ERP-GOMS Integration Workshop)
W3
FinViet đề xuất phương án (Solution Design)
W4
FinViet config (2-Phase Blueprint Sign-off)
|
W1
FinViet config (UAT Environment Setup)
W2
FinViet config (SIT ERP & GoMS)
W3
FinViet - BTM hoàn tất SIT (EOffice & GoMS)
W4
FinViet chuẩn bị đầy đủ môi trường & dữ liệu UAT, User Guide cho Key User
|
W1
FinViet chuẩn bị đầy đủ môi trường & dữ liệu UAT (Data kho, vùng miền, KH, sales, pricing, BU, CTKM, hoa hồng)
W2
FinViet phối hợp cùng Vigo thống nhất kịch bản UAT
W3
FinViet train (key user dùng DMS)
W4
FinViet support (Key user dùng thử DMS)
|
W1
FinViet support (UAT Sign-off)
W2
FinViet hoàn thành chuẩn bị môi trường, tích hợp & dữ liệu cho Go-live
W3
FinViet config & integrate ERP, EOffice (Data Migration)
W4
FinViet train (Training all users dùng DMS)
|
W1
FinViet support (Go-live Phase 1)
FinViet lấy yêu cầu nghiệp vụ (Discovery Phase 2)
W2
FinViet triển khai Pilot & xác nhận vận hành Web (Hypercare Phase 1)
FinViet lấy yêu cầu nghiệp vụ (All system Integration Workshop - Phase 2)
W3
FinViet triển khai Pilot & xác nhận vận hành App (Hypercare Phase 1)
FinViet đề xuất phương án (Blueprint Sign-off - Phase 2)
W4
Hoàn tất hỗ trợ sau Pilot (Hypercare Phase 1)
FinViet config (UAT Environment Setup - Phase 2)
|
W1
FinViet dev (Phase 2_B2B development)
W2
FinViet config (SIT & UAT)
W3
FinViet train & config (Data Import_Forecast)
W4
FinViet support (Go-live Phase 2)
|
|||
| STRAT |
W3
STRAT coordinate
W4
STRAT coordinate
|
W1
STRAT coordinate
W2
STRAT join & share
W3
STRAT coordinate
W4
STRAT prepare infrastructure
|
W1
STRAT prepare infrastructure
W2
STRAT prepare infrastructure
W3
STRAT hoàn tất SIT
W4
STRAT chuẩn bị đầy đủ môi trường & dữ liệu UAT, User Guide cho Key User
|
W1
STRAT chuẩn bị đầy đủ môi trường & dữ liệu UAT cho Key User
W2
STRAT phối hợp cùng Vigo thống nhất kịch bản UAT
W3
STRAT coordinate
W4
STRAT coordinate
|
W1
STRAT hoàn thành kiểm thử và xác nhận hệ thống
W2
STRAT tích hợp CORE MAPPING & training
W3
STRAT config
W4
STRAT xác nhận tất cả điều kiện Go-live đã sẵn sàng
|
W1
STRAT support (Go-live Phase 1)
STRAT coordinate (Discovery Phase 2)
W2
STRAT support (Hypercare Phase 1)
STRAT join & share (Integration Workshop - Phase 2)
W3
STRAT support (Hypercare Phase 1)
STRAT coordinate (Blueprint Sign-off - Phase 2)
W4
STRAT support (Hypercare Phase 1)
STRAT prepare infrastructure (UAT Environment Setup - Phase 2)
|
W1
STRAT coordinate
W2
STRAT test integration và phản hồi
W3
STRAT xác nhận tất cả điều kiện Go-live đã sẵn sàng
W4
STRAT support
|
|||
| BOD |
W1
CEO join & share (Business Requirement Workshop)
W4
CEO join & align (Blueprint Sign-off)
|
W4
CEO join & align (UAT Data Ready - Masterdata)
|
W2
CEO join & align (UAT Test Case Preparation)
|
W1
CEO join & align (UAT Sign-off)
|
W1
CEO join & share (Discovery Phase 2)
W3
CEO join & align (Blueprint Sign-off - Phase 2)
|
|||||
| FIN |
W1
FIN join & share (Business Requirement Workshop)
|
W1
FIN fill in data (UAT Data Ready)
|
W3
FIN review data (Data Migration)
|
W1
FIN phản hồi
W2
FIN phản hồi
W3
FIN phản hồi
W4
FIN xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
FIN phản hồi (Development Phase 2)
|
W1
FIN phản hồi
W2
FIN phản hồi
W3
FIN phản hồi
W4
FIN xác nhận độ hoàn thiện của GOMS
|
|||||
| ACC |
W1
ACC join & share (Business Requirement Workshop)
|
W4
ACC fill in data (UAT Data Ready)
|
W1
ACC fill in data (UAT Data Ready)
|
W3
ACC review data (Data Migration)
|
W1
ACC phản hồi - dừng MISA CRM
W2
ACC phản hồi
W3
ACC phản hồi
W4
ACC xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
ACC phản hồi (Development Phase 2)
|
W1
ACC phản hồi
W2
ACC phản hồi
W3
ACC phản hồi
W4
ACC xác nhận độ hoàn thiện của GOMS
|
||||
| HR |
W1
HR join & share (Business Requirement Workshop)
|
W1
HR fill in data (UAT Data Ready)
|
W3
HR review data (Data Migration)
|
W1
HR phản hồi
W2
HR phản hồi
W3
HR phản hồi
W4
HR xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
HR phản hồi (Development Phase 2)
|
W1
HR phản hồi
W2
HR phản hồi
W3
HR phản hồi
W4
HR xác nhận độ hoàn thiện của GOMS
|
|||||
| SALES |
W1
SALES join & share (Business Requirement Workshop)
W3
SALES align solution (Solution Design)
|
W4
SALES fill in data (UAT Data Ready)
|
W1
SALES fill in data trên CORE MAPPING (UAT Data Ready)
W2
SALES fill in data trên CORE MAPPING (UAT Test Case Preparation)
W3
SALES join training (key user dùng DMS)
W4
SALES dùng thử DMS
|
W1
SALES dùng thử DMS (UAT Sign-off)
W2
SALES dùng thử CORE MAPPING (Production Environment Setup)
W3
SALES review data (Data Migration)
W4
SALES join training (Training all users)
|
W1
SALES dùng Hệ thống DMS - dừng MISA CRM (Go-live Phase 1)
SALES phản hồi (Discovery Phase 2)
W2
SALES phản hồi
W3
SALES phản hồi
W4
SALES xác nhận độ hoàn thiện của DMS (Hypercare Phase 1)
SALES phản hồi (Development Phase 2)
|
W1
SALES phản hồi
W2
SALES phản hồi
W3
SALES phản hồi
W4
SALES xác nhận độ hoàn thiện của GOMS
|
||||
| MappingCore |
Xây dựng MVP - logic
|
Xây dựng Core Mapping Application
|
Tích hợp Goms
|
Go live
|
Review & Fixbug
|
TBU
|
TBU
|
|||
| Event Engine |
Khởi động dự án
|
Pilot đợt 1
|
Mapping MISA CRM + Export tập khách hàng
|
Chờ tích hợp Core Mapping
|
Chờ tích hợp Core Mapping
|
Chờ tích hợp Core Mapping
|
Tích hợp Core Mapping
|
Tích hợp Core Mapping
|
Go live
|
|
| Marketing Dash & MI |
Go Live MKT dash 2 BU
|
Renew Metrics account for Data extraction
|
Go Live Metrics template Overview & Competitor Jun 2025 - May 2026
|
20th
Monthly update Metrics template
|
20th
Monthly update Metrics template
|
20th
Monthly update Metrics template
|
20th
Monthly update Metrics template
|
20th
Monthly update Metrics template
|
20th
Monthly update Metrics template
|
|
| Medical Hub |
|
Develop Project + Brief vendor
|
UX/UI & Core Features
|
Web/App Development
Content Preparation
Content upload
|
MVP Review
|
Go live
|
|
|
||